Critical Challenge: National Preparedness
Our current system for homeland security does not provide the necessary framework to manage the challenges posed by 21st Century catastrophic threats. But to be clear, it is unrealistic to think that even the strongest framework can perfectly anticipate and overcome all challenges in a crisis. While we have built a response system that ably handles the demands of a typical hurricane season, wildfires, and other limited natural and man-made disasters, the system clearly has structural flaws for addressing catastrophic events. During the Federal response to Katrina3, four critical flaws in our national preparedness became evident: Our processes for unified management of the national response; command and control structures within the Federal government; knowledge of our preparedness plans; and regional planning and coordination. A discussion of each follows below.
Unified Management of the National Response
Effective incident management of catastrophic events requires coordination of a wide range of organizations and activities, public and private. Under the current response framework, the Federal government merely “coordinates” resources to meet the needs of local and State governments based upon their requests for assistance. Pursuant to the National Incident Management System (NIMS) and the National Response Plan (NRP), Federal and State agencies build their command and coordination structures to support the local command and coordination structures during an emergency. Yet this framework does not address the conditions of a catastrophic event with large scale competing needs, insufficient resources, and the absence of functioning local governments. These limitations proved to be major inhibitors to the effective marshalling of Federal, State, and local resources to respond to Katrina.
Soon after Katrina made landfall, State and local authorities understood the devastation was serious but, due to the destruction of infrastructure and response capabilities, lacked the ability to communicate with each other and coordinate a response. Federal officials struggled to perform responsibilities generally conducted by State and local authorities, such as the rescue of citizens stranded by the rising floodwaters, provision of law enforcement, and evacuation of the remaining population of New Orleans, all without the benefit of prior planning or a functioning State/local incident command structure to guide their efforts.
The Federal government cannot and should not be the Nation’s first responder. State and local governments are best positioned to address incidents in their jurisdictions and will always play a large role in disaster response. But Americans have the right to expect that the Federal government will effectively respond to a catastrophic incident. When local and State governments are overwhelmed or incapacitated by an event that has reached catastrophic proportions, only the Federal government has the resources and capabilities to respond. The Federal government must therefore plan, train, and equip to meet the requirements for responding to a catastrophic event.
Command and Control Within the Federal Government
In terms of the management of the Federal response, our architecture of command and control mechanisms as well as our existing structure of plans did not serve us well. Command centers in the Department of Homeland Security (DHS) and elsewhere in the Federal government had unclear, and often overlapping, roles and responsibilities that were exposed as flawed during this disaster. The Secretary of Homeland Security, is the President’s principal Federal official for domestic incident management, but he had difficulty coordinating the disparate activities of Federal departments and agencies. The Secretary lacked real-time, accurate situational awareness of both the facts from the disaster area as well as the on-going response activities of the Federal, State, and local players.
The National Response Plan’s Mission Assignment process proved to be far too bureaucratic to support the response to a catastrophe. Melvin Holden, Mayor-President of Baton Rouge, Louisiana, noted that, “requirements for paper work and form completions hindered immediate action and deployment of people and materials to assist in rescue and recovery efforts.”4 Far too often, the process required numerous time consuming approval signatures and data processing steps prior to any action, delaying the response. As a result, many agencies took action under their own independent authorities while also responding to mission assignments from the Federal Emergency Management Agency (FEMA), creating further process confusion and potential duplication of efforts.
This lack of coordination at the Federal headquarters-level reflected confusing organizational structures in the field. As noted in the Week of Crisis chapter, because the Principal Federal Official (PFO) has coordination authority but lacks statutory authority over the Federal Coordinating Officer (FCO), inefficiencies resulted when the second PFO was appointed. The first PFO appointed for Katrina did not have this problem because, as the Director of FEMA, he was able to directly oversee the FCOs because they fell under his supervisory authority.5 Future plans should ensure that the PFO has the authority required to execute these responsibilities.
Moreover, DHS did not establish its NRP-specified disaster site multi-agency coordination center—the Joint Field Office (JFO)—until after the height of the crisis.6 Further, without subordinate JFO structures to coordinate Federal response actions near the major incident sites, Federal response efforts in New Orleans were not initially well-coordinated.7
Lastly, the Emergency Support Functions (ESFs) did not function as envisioned in the NRP. First, since the ESFs do not easily integrate into the NIMS Incident Command System (ICS) structure, competing systems were implemented in the field – one based on the ESF structure and a second based on the ICS. Compounding the coordination problem, the agencies assigned ESF responsibilities did not respect the role of the PFO. As VADM Thad Allen stated, “The ESF structure currently prevents us from coordinating effectively because if agencies responsible for their respective ESFs do not like the instructions they are receiving from the PFO at the field level, they go to their headquarters in Washington to get decisions reversed. This is convoluted, inefficient, and inappropriate during emergency conditions. Time equals lives saved.”
Knowledge and Practice in the Plans
At the most fundamental level, part of the explanation for why the response to Katrina did not go as planned is that key decision-makers at all levels simply were not familiar with the plans. The NRP was relatively new to many at the Federal, State, and local levels before the events of Hurricane Katrina.8 This lack of understanding of the “National” plan not surprisingly resulted in ineffective coordination of the Federal, State, and local response. Additionally, the NRP itself provides only the ‘base plan’ outlining the overall elements of a response: Federal departments and agencies were required to develop supporting operational plans and standard operating procedures (SOPs) to integrate their activities into the national response.9 In almost all cases, the integrating SOPs were either non-existent or still under development when Hurricane Katrina hit. Consequently, some of the specific procedures and processes of the NRP were not properly implemented, and Federal partners had to operate without any prescribed guidelines or chains of command.
Furthermore, the JFO staff and other deployed Federal personnel often lacked a working knowledge of NIMS or even a basic understanding of ICS principles. As a result, valuable time and resources were diverted to provide on-the-job ICS training to Federal personnel assigned to the JFO. This inability to place trained personnel in the JFO had a detrimental effect on operations, as there were not enough qualified persons to staff all of the required positions. We must require all incident management personnel to have a working knowledge of NIMS and ICS principles.
Insufficient Regional Planning and Coordination
The final structural flaw in our current system for national preparedness is the weakness of our regional planning and coordination structures. Guidance to governments at all levels is essential to ensure adequate preparedness for major disasters across the Nation. To this end, the Interim National Preparedness Goal (NPG) and Target Capabilities List (TCL) can assist Federal, State, and local governments to: identify and define required capabilities and what levels of those capabilities are needed; establish priorities within a resource-constrained environment; clarify and understand roles and responsibilities in the national network of homeland security capabilities; and develop mutual aid agreements.
Since incorporating FEMA in March 2003, DHS has spread FEMA’s planning and coordination capabilities and responsibilities among DHS’s other offices and bureaus. DHS also did not maintain the personnel and resources of FEMA’s regional offices.10 FEMA’s ten regional offices are responsible for assisting multiple States and planning for disasters, developing mitigation programs, and meeting their needs when major disasters occur. During Katrina, eight out of the ten FEMA Regional Directors were serving in an acting capacity and four of the six FEMA headquarters operational division directors were serving in an acting capacity. While qualified acting directors filled in, it placed extra burdens on a staff that was already stretched to meet the needs left by the vacancies.
Additionally, many FEMA programs that were operated out of the FEMA regions, such as the State and local liaison program and all grant programs, have moved to DHS headquarters in Washington. When programs operate out of regional offices, closer relationships are developed among all levels of government, providing for stronger relationships at all levels. By the same token, regional personnel must remember that they represent the interests of the Federal government and must be cautioned against losing objectivity or becoming mere advocates of State and local interests. However, these relationships are critical when a crisis situation develops, because individuals who have worked and trained together daily will work together more effectively during a crisis.
Lessons Learned:
The Federal government should work with its homeland security partners in revising existing plans, ensuring a functional operational structure - including within regions - and establishing a clear, accountable process for all National preparedness efforts. In doing so, the Federal government must:
w Ensure that Executive Branch agencies are organized, trained, and equipped to perform their response roles.
w Finalize and implement the National Preparedness Goal.